ALE complete first phase of Doha Metro Project

ALE has moved 1,470 heavy items to successfully complete the first phase of the new Doha metro project in June 2016.

The global heavy lifting experts were contracted to move the items as part of the Qatar Rail infrastructure development project.

The heavy items ranged in weight between 50t – 300t, (10m to 36m long) and comprised of pre-tensioned concrete pedestal, girder, bridging and segment structures that were all pre-fabricated on site.

ALE collected the items from the fabrication area and delivered to the crane hook at the installation point. The journey ranged between 50m and 8km, across challenging roads that changed daily. To keep up with the demanding schedule ALE utilised 34 axle line of conventional trailers, 3 x 10 axle extendable semi-trailers, 6 prime movers and 24 axle lines of SPMT for the complex final deliveries.

All items were delivered on schedule and it took 11 months to complete the first phase of Qatar Rail infrastructure development project.