Filters
Go back

Hitachi EX1900-6 increases productivity at UK quarry

Tarmac has invested in a Hitachi EX1900-6 ultra-large excavator for its Swinden Quarry in North Yorkshire. The site’s new primary mover is helping to reduce operational hours at the site by increasing productivity and efficiency.

Advertisement

The EX1900-6 is used to load up to 1,200 tonnes of carboniferous limestone per hour directly into a 200-tonne mobile crusher. A field conveyor takes the material to a secondary crusher at an average rate of 1,000 tonnes per hour.

The Hitachi model was supplied with a longer boom and arm, and a smaller 8.0m3 bucket, than is customary on a machine of this size. “This is because it needs a larger working range to reach the limestone and load the crusher,” says Mark Turnham, Mines & Quarries Manager at Hitachi Construction Machinery (UK). “It means the primary crusher doesn’t need to be moved as frequently – this can take 45 minutes – so it enhances the efficiency of the process.”

The ultra-large excavator was also supplied with Hitachi Genuine Ground Engaging Tools, which further enhance productivity by improving penetration and overall digging power. The edge shrouds for the bucket and Long Penetration teeth are manufactured from high-grade steel and tested to the same standard as all Hitachi construction equipment.

Swinden Quarry produces various sizes of aggregates, from 100mm down to dust (including grades of 80, 40, 28, 20, 14, 10 and 6), which are dry stored in silos. The material is either directly transferred to the site’s rail siding via a conveyor to the fully automated lorry load-out, or into the ‘toast rack’ storage, from which a wheel loader can directly load customers’ trucks.

Approximately 60% of the materials are transported by rail to Tarmac’s dry distribution centres in Leeds, for onward transportation to South Yorkshire, and a depot in Hull. Much of the limestone is used in Tarmac’s concrete and asphalt plants in the north of England.

With the arrival of the EX1900-6, Tarmac intends to maintain its current production levels and annual output of 2.3 million tonnes. Quarry Manager Jez West explains: “During the tender process, we looked at productivity and fuel consumption. We wanted to reduce operational hours by increasing productivity.”

Operator George Metcalf has been impressed by the speed and productivity of the machine, which was delivered in November 2015. “It’s faster than other machines I’ve used and has good all-round visibility. The cab feels more open and spacious, the seat is comfortable, and the controls are easy to use.”

Source: Red International Communication

Hitachi EX 1900-6 on LECTURA Specs