Filters
Go back

Sustainable pavement rehabilitation and road widening in a single pass with cold recycling

The cold recycling train deployed as a Wirtgen Group production system rehabilitated the Sinding Hedevej near Silkeborg in a single pass.
Wirtgen (Wirtgen Group) Europe
Go to photo
The cold recycling train deployed as a Wirtgen Group production system rehabilitated the Sinding Hedevej near Silkeborg in a single pass.

IMAGE SOURCE: WIRTGEN GROUP

 

  • Cold recycling train rehabilitated and widened a road in Silkeborg, Denmark in a single pass

  • New base layer completed and opened to traffic in just four days

  • Process was extremely fast and cost-efficient compared to conventional asphalt paving methods

  • In-place cold recycling used existing asphalt material for production of a new BSM base layer

  • Cold recycler milled off existing asphalt pavement and added foamed bitumen and cement to produce new mix

  • Road paver then paved new pavement profile in one pass

  • Construction costs were 30% lower than conventional rehabilitation projects

  • Savings on materials played a significant role in cost reduction

  • Foamed bitumen technology reduced the amount of bitumen needed as a binding agent

  • Final asphalt surface layer was thinner than usual, further reducing costs

  • Lower haulage costs resulted in additional savings and reduced carbon emissions

  • Recycling area produced 4,000 t of material that did not need to be removed from the site

  • Overall CO₂ emissions were reduced by up to 70%

  • Cold recycling with foamed bitumen is a standard practice in road construction worldwide

  • Provides durable BSM mixes for more sustainable road construction

  • Guarantees a reduction in CO₂ emissions and overall costs for primary resources.

Production system delivers impressive results on a project in Silkeborg/Denmark

Advertisement

What surprised local residents, the municipal authorities and construction engineers was just another job for the cold recycling experts from the lead contractor. Because the cold recycling train deployed as a Wirtgen Group production system and led by the W 380 CRi rehabilitated and widened the Sinding Hedevej near Silkeborg in a single pass. New base layer completed and opened to traffic after only four days

Extremely fast and cost-efficient

Using conventional asphalt paving methods, the process would have involved milling off the entire road surface in several stages and then widening and repaving the roadway from the ground up. In contrast, in-place cold recycling used the existing asphalt material on the spot for the production of a qualitatively new BSM base layer. The Wirtgen W 380 CRi cold recycler first milled off the existing asphalt pavement to a depth of 15 cm and then added foamed bitumen and cement to the milled material to directly produce the new mix in the machine’s milling and mixing chamber. Approximately 300 t of BSM (bitumen stabilised material) per hour were transferred to the Vögele SUPER 2100-3i road paver following on behind, which then paved the new pavement profile to a width of 5.5 m and a depth of 12 cm in one single pass. The cold recycling train worked its way forward along the 3 km section of the Sinding Hedevej at a rate of 4 m/min. The road was able to be temporarily reopened for local road users immediately after the Hamm rollers had completed the final compaction.
The Wirtgen W 380 CRi processes the pre-milled and prepared material and transfers the homogeneous BSM mix directly into the material hopper of the Vögele paver.<br>IMAGE SOURCE: WIRTGEN GROUP

Considerably lower construction costs

According to lead contractor Arkil A/S, the costs were 30 per cent lower than for a conventional rehabilitation project. In view of this, the municipal authorities in Silkeborg are already planning the next road construction project with the cold recycling method.

Savings on materials played the biggest role in the reduction of the overall project costs. Thanks to foamed bitumen technology from Wirtgen, considerably less bitumen needs to be added as a binding agent than would be required for the production of new asphalt mix. Hot bitumen was delivered to the site and automatically injected in-place – i.e. during the milling and mixing process – via the Vario injection bar. Thanks to process-dependent machine control, the feed volume was directly matched to the travel speed of the machine and ensured the homogeneity of the mix transferred directly to the SUPER 2100-3i paver.

Another advantage: the final asphalt surface layer can be paved thinner than usual. In this case, only 3 cm of the high quality surface layer material was used, instead of the usual 4 to 5 cm. This also helped to reduce the overall construction costs.
The versatility and durability of BSM have been proven on decades of projects around the globe. The required minimum thickness for a sustainable BSM base layer is 10 cm, in Silkeborg, the SUPER 2100-2i paved the material with a thickness of 12 cm.<br>IMAGE SOURCE: WIRTGEN GROUP

The reduction of the site logistics required results in lower carbon emissions

Lower haulage costs led to further cost savings. The recycling area of over 12,000 m2 produced almost 4,000 t of material that did not have to be removed from the site. Two factors in particular played a role in the reduction of CO₂ emissions: firstly, the elimination of the movement of a calculated 400 truckloads of material to and from the site and, secondly, a considerable reduction of the 3,800 t of fresh hot-mixed-asphalt that would have had to be produced for the base layer in the case of conventional asphalt paving. According to Arkil, these factors enabled an up to 70% reduction of the overall CO₂ emissions.

‘Essentially, cold recycling is suitable for the rehabilitation of all kinds of roads. It was particularly good here, as no material had to be moved to or from the site and we were also able to widen the roadway as well in a single pass. And that seriously reduces our carbon footprint’, emphasises Mikkel Caprani, Site Manager from Arkil A/S.
A Hamm DV+90i VV delivers the compaction required to ensure protection of the road surface.<br>IMAGE SOURCE: WIRTGEN GROUP

High worldwide demand for cold recycling with foamed bitumen

Thanks to the clear advantages of cold recycling with foamed bitumen, it has already become established as a standard practice in road construction in many parts of the world. Whether for in-place rehabilitation, as here in Silkeborg with a CR-series cold recycler, full-depth recycling (FDR) through and below the base layer with a WR-series wheeled recycler or decentralised in-plant mixing in a cold recycling asphalt mixing plant such as the KMA 240(i), foamed bitumen technology delivers extremely durable BSM mixes for more sustainable road construction. What’s more, no matter which cold recycling method is chosen and which Wirtgen Group production system is used, a considerable reduction of CO₂ emissions and overall costs for primary resources is consistently guaranteed.

 

Source: WIRTGEN GROUP

Get in touch with Wirtgen (Wirtgen Group)

WIRTGEN GROUP

Address

Reinhard-Wirtgen-Str. 2
53578 Windhagen | Germany

Email

info@wirtgen-group.com

Website

www.wirtgen-group.com