Filters
Go back

Tandem hoist on cellar ceiling: Haslach installs giant prestressed concrete trusses

The Vorarlberg Alps as a backdrop, framed by a Liebherr tower crane: two Liebherr mobile cranes from Kranverleih Haslach erected a total of ten prestressed concrete trusses for the construction of a new hall in Bludenz. The hall floor with cellar made the job a challenge.
Liebherr Europe
Go to photo
The Vorarlberg Alps as a backdrop, framed by a Liebherr tower crane: two Liebherr mobile cranes from Kranverleih Haslach erected a total of ten prestressed concrete trusses for the construction of a new hall in Bludenz. The hall floor with cellar made the job a challenge.

IMAGE SOURCE: Liebherr-Werk Ehingen GmbH

  • Haslach successfully installed several 98-tonne prestressed concrete trusses in Bludenz for the Getzner textile factory's new hall.

  • The project involved extensive planning and stabilizing the cellar ceiling to support the LTM 1300-6.3 crane.

  • A tandem hoist was executed using an LTM 1230-5.1 crane set up on a specially filled embankment outside the hall.

  • Both cranes operated at maximum capacity to lift the trusses, each handling 51 tonnes with a radius of 13 and 15 meters.

  • The transport of the 47.3-meter-long trusses required special permits and was conducted at night.

  • Operations at the Getzner textile factory continued uninterrupted, and the collaboration on-site was highly praised by Tobias Haslach.

 

  • Liebherr LTM 1230-5.1 and LTM 1300-6.3 from Haslach install prestressed concrete trusses

  • Prestressed concrete trusses weighing just under 100 tonnes and measuring 42 metres in length

  • LTM 1300-6.3 operates on a hall floor with cellar underneath

Advertisement

Haslach achieved successful deployment with a lot of planning: several prestressed concrete trusses weighing just under 100 tonnes were installed in the Austrian town of Bludenz for the construction of a new hall at the Getzner textile factory. The hall floor with full cellar running underneath and the limited footprint made the deployment a considerable challenge.

Heads were spinning during the planning: the objective was to install ten prestressed concrete trusses, each weighing 98 tonnes, for the roof in a hall that had a cellar running underneath. The hall floor's support load was limited, and space was also very restricted. Getzner's deliveries also had to continue uninterrupted. Tobias Haslach, owner of Kranverleih Haslach GmbH, recalls: “After extensive planning and many detailed calculations, we were able to come up with a solution for the installation work in conjunction with the other companies involved. We stabilised the cellar ceiling from underneath with ceiling supports in order to achieve the support strength required to allow our LTM 1300-6.3 to work on this cellar ceiling.” Alongside the 6-axle mobile crane, the special transport also drove onto the cellar ceiling to unload the 98-tonne concrete truss.

When lifting the 42-metre-long truss from the truck, both mobile cranes were at maximum capacity with a load of 51 tonnes each<br>IMAGE SOURCE: Liebherr-Werk Ehingen GmbH

Haslach used an LTM 1230-5.1 as the second crane for the tandem hoist. Tobias Haslach recounts the challenges: “We set up the 5-axle vehicle on a specially filled embankment outside the hall. Due to the positioning behind a concrete wall, we were only able to coordinate with the work team via radiotelephony. The truss also had to be guided around the LTM 1300-6.3.” When lifting the truss from the truck, both mobile cranes were working at maximum capacity with a load of 51 tonnes each and a radius of 13 metres and 15 metres respectively. Two reinforced concrete trusses were installed in one day. With a length of 47.3 metres and a total weight of 148 tonnes, the transport required a special permit and was only allowed to travel at night. After each installation, both mobile cranes were moved with all their equipment including ballast and positioned for the lifting of the subsequent reinforced concrete trusses.

Poor visibility: the LTM 1230-5.1 had to be positioned behind a wall. The coordination via radio worked smoothly.<br>IMAGE SOURCE: Liebherr-Werk Ehingen GmbH

“The cooperation on the construction site was excellent. Operations at the Getzner textile factory continued virtually undisturbed. Our two crane operators were also delighted with the collaboration of everyone involved on site,” says Tobias Haslach. The family-run company Kranverleih Haslach is based in Wertach in southern Germany and relies entirely on Liebherr for its nine mobile cranes.

Source: Liebherr-Werk Ehingen GmbH