Bridging Riyadh – Three WOLFF cranes build two cable-stayed bridges in Saudi Arabia's capital

Three WOLFF 180 B luffing jib cranes handle all lifting operations
during the construction of the bridge pylons, which reach heights
of up to around 170 meters. The crane operations must be closely
coordinated with the climbing sequence of the formwork and
working platforms.
WOLFFKRAN Europe, International
Go to photo
Three WOLFF 180 B luffing jib cranes handle all lifting operations during the construction of the bridge pylons, which reach heights of up to around 170 meters. The crane operations must be closely coordinated with the climbing sequence of the formwork and working platforms.

IMAGE SOURCE: WOLFFKRAN International AG

  • Three WOLFF 180 B luffing jib cranes with 40-meter jibs and 18-ton lifting capacity are used to build two new cable-stayed bridges in Riyadh.

  • The cranes handle complex lifting tasks including formwork, reinforcement, concrete placement, and heavy support beams for four pylons up to 170 meters tall.

  • The bridges will each be approximately 763 meters long with a 405-meter main span and accommodate eight traffic lanes.

  • This project is part of Riyadh's Main and Ring Road Axes Development Program, aiming to improve the city's traffic infrastructure by 2027.

For over 30 years, the Wadi Laban Bridge was the only crossing of the valley of the same name in the southwest of Saudi Arabia’s capital, Riyadh. Now, the existing crossing is being complemented by two new cable-stayed bridges, which are being constructed on both sides of the current bridge. The client is the Royal Commission for Riyadh City, and the project is being executed by the ICRC joint venture consisting of the Turkish construction company IC Ictas and the Al Rashid Trading & Contracting Company (RTCC) from Riyadh. At the major construction site in the middle of Riyadh’s desert landscape, three WOLFF 180 B luffing jib cranes are being used, handling all lifting tasks – from formwork and reinforcement to concrete placement.

The three WOLFF cranes, each equipped with 40-meter jibs, reach a hook height of 157 meters and have a maximum lifting capacity of 18 tons. They are being used to construct four bridge pylons, which are up to approx. 170 meters high, and handle formwork systems, and transport reinforcement, as well as carrying out concrete pouring. In addition, they lift work platforms, surveying equipment, and other construction site gear. A particular challenge was the simultaneous repositioning of several stacked working platforms when changing the formwork between different pylon sections during which they fully utilized their maximum load capacity of 18,0 tons. As construction progresses, the cranes will also lift support beams weighing up to 12,0 tons for the concreting of the pylon heads.

In the midst of the desert landscape southwest of Riyadh, threeWOLFF 180 B luffing jib cranes are supporting the construction ofthe new cable-stayed bridges over the Wadi Laban Valley. Theconstruction project is part of a large-scale infrastructure initiativein Riyadh that, according to official statements, is expected toincrease the capacity of the road network by up to 85 percent inthe long term.<br>IMAGE SOURCE: WOLFFKRAN International AG

Gigantic structures for improved mobility

The three WOLFF 180 B luffing jib cranes were assembled in 2025 using mobile cranes and are expected to remain in operation on the construction site until 2027. Once completed, the two new cabled-stayed bridges will each have a total length of around 763 meters and a main span of 405 meters. With a width of about 35 meters, they are designed for a total of eight traffic lanes and will significantly increase the capacity of this important arterial road in Riyadh. The new construction is part of the “Main and Ring Road Axes Development Program,” a comprehensive expansion initiative for the capital’s main traffic routes.

Source: WOLFFKRAN International AG