Filters
Go back

VARIOKIT VTC Tunnel Formwork Carriage supports construction of Werrington Grade Separation tunnel

The 160 m long tunnel was cast monolithically in a total of nine sections - with only one VTC Tunnel Formwork Carriage.
PERI Europe
Go to photo
The 160 m long tunnel was cast monolithically in a total of nine sections - with only one VTC Tunnel Formwork Carriage.

IMAGE SOURCE: PERI GmbH

For the construction of the Werrington Grade Separation tunnel, the VARIOKIT VTC Tunnel Formwork Carriage and other PERI standard components were used for a solution which, despite its rectangular structure, delivered a curved result. Optimally coordinated formwork and scaffolding solutions from a single source, as well as clever advance planning services, ensured that the project ran smoothly.

The aim of the Werrington Grade Separation in Cambridgeshire was to improve the railway infrastructure. By tunnelling under the existing line with the new railway line, the capacity of the East Coast Main Line should be increased and travel times reduced.

The curved, around 160 m long tunnel was cast monolithically with just a single rectangular tunnel formwork carriage. During a nine-day closure of the railway line in January 2021, the structure was lifted into position.

With a customised VTC Tunnel Formwork Carriage, consisting of standard components from the VARIOKIT Engineering Construction Kit in combination with GT 24 Girders and Battens in different lengths, the project requirements could be met. <br> Image source: PERI GmbH

Working together on a coordinated solution

PERI´s customer Bell Formwork ltd needed a solution that would allow them to complete the tunnel quickly, efficiently and without increased material costs. In order to design this solution together, an international team of PERI engineers from the United Kingdom and Germany was involved in this project from the very beginning and combined their expertise from past projects.

With a customised VTC Tunnel Formwork Carriage, consisting of standard components from the VARIOKIT Engineering Construction Kit in combination with GT 24 Girders and battens in different lengths, the project requirements could be met. Not only did the system form the tunnel´s curvature, it also reduced the amount of special formwork to a minimum as only one tunnel formwork carriage was required.

In total, the tunnel was cast in nine concreting sections, each 17 m long and 8 m high. The combination of concreting sequence and the high speed of the VTC System helped to save a full ten days per cycle. <br> Image source: PERI GmbH

Immense time savings thanks to the use of hydraulics

The hydraulics of the VTC Tunnel Formwork Carriage played an important role during the project: it allowed the client to quickly and safely strike both undersides and inner slabs at the same time and move on to the next section without having to dismantle and reassemble the tunnel formwork carriage. Once the system was up and running, only minimal adjustments were needed beyond that. In total, the tunnel was thus cast in nine concreting sections, each 17 m long and 8 m high. The combination of concreting sequence and the high speed of the VTC System helped to save a full ten days per cycle.

With the help of the VTC Tunnel Formwork Carriage used, both undersides and inner slabs could be quickly and safely struck at the same time. <br> Image source: PERI GmbH

Formwork and scaffolding solution from a single source

In order to allow access to the slab undersides, a movable stair tower consisting of components from the PERI UP Scaffolding Kit was integrated at the front end of the formwork solution. This could be moved together with the VTC Tunnel Formwork Carriage. PERI UP´s compatibility with the formwork solution enabled seamless access for operatives as it continued travelling with the VTC carriage to each casting section.  This minimised the installation effort and saved valuable time on site. 

 

Source: PERI GmbH