The Elleringhauser Tunnel in Germany is undergoing a complete renovation, requiring the removal of concrete cable ducts.
-
The EET consortium, comprising Max Bögl, Marti DE, and Marti CH, is executing the renovation using a tunnel-within-a-tunnel method to avoid prolonged closures.
-
An 8-tonne compact excavator equipped with a KEMROC KDS 30 diamond saw was chosen for its suitability in the tunnel's narrow space and operational constraints.
-
The KEMROC KDS 30 diamond saw, known for cutting various materials, proved effective in cutting through the concrete ducting quickly and efficiently.
-
The cutting process involved setting up the diamond saw at intervals, cutting through the duct, and then using a hydraulic hammer and grab to remove the concrete sections.
-
The project was completed faster than planned, validating the choice of equipment and showcasing the versatility of KEMROC's attachments.
Making room for new tunnel lining
The Elleringhauser Tunnel in Germany’s Hoch Sauerland region is being completely renovated. To install new tunnel lining, concrete cable ducts had to be removed from the bottom of the tunnel wall. Specialists from the EET consortium (Max Bögl/Marti DE/Marti CH) chose an 8-tonne compact excavator and a KEMROC KDS 30 diamond saw to cut the concrete ducting into manageable pieces.
The Elleringhauser Tunnel in the Hoch Sauerland (North Rhine-Westphalia) has a long history. The almost 1,400 m long railway tunnel near Olsberg and Brilon is part of the Upper Ruhr Valley Railway, which runs between Aachen and Kassel. Between 1868 and 1872, the tunnel was built as a single tube with double track. The tunnel – a classic masonry structure in a horseshoe shape – has to be renovated after almost 150 years of use. Three contracting companies Max Bögl Stiftung & Co. KG, Marti GmbH Deutschland and Marti Tunnel AG joined forces to form the ARGE Elleringhauser Tunnel (EET consortium).
Most of the renovation work will be carried out using the so-called tunnel-within-a-tunnel method, which avoids full closure over longer periods of time. Initially, the existing masonry will be profiled before a new prefabricated tunnel lining will be installed. To create the necessary space for the new tunnel lining, existing concrete cable ducts for signalling and lighting technology located on both sides of the tunnel floor must first be removed.
Dipl.-Ing Thomas Töpfer, mechanical engineer from ARGE partner Max Bögl, explained the logic behind their choice of equipment: "Using an excavator with concrete shearer or pulveriser was out of the question due to the lack of space in this tunnel with its narrow clearance profile. In addition, the renovation work takes place only at night, between 10:00 p.m. and 5:00 a.m., with the railway operating. Therefore, the standard method of core drilling and diamond cutter or wire saws would not be practical, because the equipment used would have to be set up and dismantled over and over again." For this reason, those involved in the consortium opted for a solution that is unusual in tunnel construction – namely the use of diamond saw technology in the form of a rented mini excavator with a diamond saw from the KDS range of attachments from the manufacturer KEMROC.
Fast cuts
KDS diamond saws from KEMROC are designed for cutting a wide variety of materials including natural stone, granite, reinforced concrete, concrete, asphalt, plastics, wood, foils and aluminium. Mounted on crawler or wheeled excavators and connected to their hydraulic circuit, the attachments deliver high performance in many industrial sectors with very low stress to the carrier, operator or the environment. High rotation speeds and a selection of diamond cutting wheels make these attachments very effective in a wide range of applications.
At the Elleringhauser Tunnel renovation project, the 8-t compact excavator with a KEMROC KDS 30 diamond saw (80 kW nominal power) combination proved to be very practical: On the one hand, the compact excavator was small enough to move safely in the tunnel cross-section. On the other hand, the diamond saw has a sufficiently large diameter cutting wheel to cut through the concrete ducting (height x depth = 60 x 40 cm) completely.
The cutting process in detail: The mini excavator is taken into the tunnel on a platform truck. At 150 cm intervals, the diamond saw is set up in front of the cable ducting at the bottom of the tunnel wall. Then the operator cuts through the concrete duct from top to bottom, switches to a hydraulic hammer and lifts off the portion of concrete with three or four blows. He then switches to a grab and loads the concrete section for removal from the tunnel.
The cutting work lasted from January 8 to 27, 2024 – significantly quicker than initially planned. For Thomas Töpfer, the results confirmed that the choice of equipment was correct: "We are familiar with milling attachments and have experience using KEMROC's range of equipment in previous projects, for example in tunnel and asphalt road construction. It's good to know that the manufacturer's range also includes attachments not originally intended for tunnelling applications, but they can be just the right solution in certain cases like this."